Showing posts with label State Infrastructure. Show all posts
Showing posts with label State Infrastructure. Show all posts

February 7, 2008

Fire LyndoTippett - It's time for him to go

North Carolina's DOT has found itself behind the bulls eye once again after a new state auditor's report reveals that the department has incurred additional costs on behalf of NC taxpayers to the tune of an extra $152 million over the last three years on 390 completed projects. The extra costs are related to mismanagement, poor planning and because of schedule changes, environmental reviews and design changes. The report states that 73 percent of those projects missed their projected construction starts. Forty percent of the projects missed that mark by more than a full year.

According to Les Merritt, NC's State Auditor, "DOT is a multi-billion dollar state agency that appears to operate on hunches and intuition rather than hard data analysis. As a result, taxpayers paid $152.4 million in unnecessary construction costs."

Merritt's report indicated that the auditors found that DOT does not track or analyze delays or successes in its road-building projects, despite repeated warnings and recommendations during the past 10 years from auditors and consultants. The auditors also said that if the department had an effective system for tracking performance, officials might have seen that delays cost taxpayers over $150 million.

"The lack of performance management practices has been pointed out to DOT before," the auditors wrote.

As expected, DOT officials are disputing the findings rather than admitting they happened and are not focusing on working toward solutions. Debbie Barbour, director of preconstruction for the department, claims engineers have only a rough guess of how long a project will take when funding is approved and says the detailed engineering has not been done up front (as it should be). She states that since the engineering work has been done at approval time, the estimated completion date can't take into account problems along the way. She also argues that environmental problems, obtaining permits and other issues are out of control of the department and says it is unfair to say projects are late because of those and other issues.

Signs continue to surface that the DOT is a poorly managed organization and unacceptable practices from the top down cause virtually everything DOT touches to be poorly done, to introduce avoidable significant problems and delays into projects and to cause taxpayers to pay more for substandard work that does not meet growing needs of the state.

It's time for Governor Easley, who takes much of his direction from his staff of buddies that help him make unwise choices and appointments of "good old boys" to state leadership positions, to realize the severity of problems in DOT and other state organizations and fire top leaders like Lyndo Tippett and mid-level management people like Debbie Barbour and at least make a feeble effort to re-establish a little control and get something for the billions of dollars spent on roads and projects while he is still in office.

Read the full article about findings in the study...

News and Observer
February 7, 2008
Dan Kane and Benjamine Niolet, Staff Writers
Delayed road projects cost millions

An audit of three years of completed state Transportation Department projects found many of them finished behind schedule, leading to what auditors say is an additional $150 million in inflation-related construction costs.

"DOT is a multi-billion dollar state agency that appears to operate on hunches and intuition rather than hard data analysis," State Auditor Les Merritt said. "As a result, taxpayers paid $152.4 million in unnecessary construction costs."

The 43-page audit released today looked at 390 highway projects completed between April 2004 and March 2007. Auditors said that 73 percent of those projects missed their projected construction starts. Forty percent of the projects missed that mark by more than a full year, Merritt said.

The audit said that the permitting process, environmental reviews and design changes caused many of the delays.

Department officials say the auditors held the department to an unfair standard. The $150 million figure is oversimplified and doesn't account for some $80 million the department saved by expediting projects within the same time frame.

The auditors based a project's start date and projected completion date on when the transportation board approved money for preliminary engineering. The problem with that method, said Debbie Barbour, director of preconstruction for the department, is that engineers have at that time only a rough guess over how long a project will take. Since no engineering work has been done, the estimated completion date can't take into account problems along the way.

"In developing a project, there are certain things that are outside the department's control, such as obtaining an environmental permit," Barbour said. "We don't really have control of the time frame on every activity in the approval process."

The auditors found that the department does not track or analyze delays or successes in its road-building projects, despite repeated warnings and recommendations during the past 10 years from auditors and consultants. The auditors said that if the department had an effective system for tracking performance, officials might have seen that delays cost taxpayers $150 million.

"The lack of performance management practices has been pointed out to DOT before," the auditors wrote.

But department officials say the department has implemented several new programs and processes since 2001 that wouldn't have been evident in the time period the auditors examined. The department has worked with the state Department of Environment and Natural Resources to streamline environmental permitting. The department measures whether it met target dates for acquiring property for a project or opening bids.

And the department has spent $3.6 million to hire a consultant to help officials change the way the department does business.

Bill Rosser, the state highway administrator said that the department works hard to finish projects on time, but road building is a complex and expensive business. Rosser said if the auditors looked at a newer set of projects, the findings would be much different.

"We would like to be responsive and deliver our projects," Rosser said. "We're always looking at the way the process works." Original source ...

February 3, 2008

NC's poor roads tied to bad politics, poor management and Governor Easley's bad choices

News continues to flow regarding North Carolina DOT's inability to solve major funding issues and failure to avoid major problems providing safe and adequate roads for the state. Under the leadership of Governor Easley's appointee, Lyndo Tippett, the organization continues business as usual with more of the same after promising to get advice from a consulting firm to help solve internal problems.

News broke in late January about another costly failure on the new I-795 between Wilson and Goldsboro rivaling the botched I-40 scandal that cost taxpayers some $22 million to repair in 2007. The new I-795 road is crumbling under weight of traffic after only two years of service and will likely cost some $7 million more to the state's taxpayers.

The latest report indicates the department's problems are still strongly tied to politics and fund raising issues that continue even after attempts by the state to separate politics and fund raising from the DOT organization 10 years ago, force disclosure of members fund raising records and require the board have members
with special skills in such fields as the environment and mass transit. Even that effort has failed and board membership "remains a plum spot for big political fundraisers who continue to ignore conflicts of interest and the wider needs of the state beyond their own districts"...
News & Observer
Dan Kane and Benjamin Niolet, Staff Writers
February 03, 2008

N.C. road building still mired in politics

Reforms in a 1998 law have failed to separate the state Board of Transportation from political fundraising

Nearly 10 years ago, state legislators championed a series of reforms for the scandal-plagued N.C. Board of Transportation that were intended to take the politics out of building roads.

Future appointees would have to disclose their political fundraising. Five of the 19 seats would be reserved for people with special skills in such fields as the environment and mass transit. Members would have to avoid even the appearance of a conflict of interest.

"The board's policies, effectiveness and integrity are important to almost every citizen," Beverly Perdue, then a state senator, said on Sept. 23, 1998, the day the bill cleared the legislature. "The public has demanded reform, and this bill lays the groundwork."

That groundwork has proven a weak foundation. A decade after Perdue hailed the reform law, the 19-member DOT board remains a plum spot for big political fundraisers who continue to ignore conflicts of interest and the wider needs of the state beyond their own districts.

For example:

* The fundraising disclosure rule is toothless. The only fundraising that board members must disclose is contributions directly handed to them. Asking people to give to a campaign or holding fundraisers -- two common ways to raise campaign money -- aren't considered fundraising on disclosure forms.

* Two of the five seats intended to bring more professionalism to the board have been given to fundraisers best known for running restaurant chains.

* Conflicts of interest continue to surface. Last month, board member Thomas Betts Jr. of Rocky Mount resigned after he sought to raise $20,000 in campaign money from country singer Randy Parton and the others behind the struggling performing arts theater in Roanoke Rapids. Betts had directed $2.5 million in road work to the theater over the previous year. He sought campaign money for Perdue, now lieutenant governor, who is seeking to be the next governor.

* Some at-large members, who are supposed to look out for the entire state, are steering their discretionary money to their home districts.

The board oversees a department with a $3.8 billion budget and a serious public image problem. A chorus of lawmakers, public policy advocates and even transportation department employees say that the department is dysfunctional -- at a time when the state's transportation needs are growing dramatically. A special "blue ribbon" legislative panel is meeting to figure out how to get the department back on track.

The department even bungled trying to fix itself. It hired a consultant at a cost of $3.6 million to help assess its strengths and weaknesses and foster change. But the department refused to disclose the terms of the contract and any findings until Gov. Mike Easley ordered them made public.

The board's makeup and activities have emerged as a campaign issue in the gubernatorial election. Perdue's rival for the Democratic nomination, State Treasurer Richard Moore, has made it a key part of his campaign. Last month, among other proposals, he announced that he would not appoint fundraisers to the board. Perdue has not called for banning fundraisers from the board.

Ten years ago, Perdue's DOT reform bill won favor over a stricter bill initially filed in the House that would have banned fundraisers from the board, required five experts in various areas, and taken away the governor's power to appoint the transportation secretary.

Last month, Easley said trying to ban fundraisers from the process would just push the money underground.

"When you get into the fundraising business, if people want to participate, they'll find a way, just like the squirrel into the bird feeder," Easley said. "I want to know how much somebody's given who's been appointed and I think people want to know as well."

Finding wiggle room

But when Easley was elected governor in 2000, two years after the reform bill passed, he quickly found wiggle room in the transportation reform law. Easley's counsel, Hampton Dellinger, asked Grayson G. Kelley, a senior deputy attorney general, for an interpretation of what made someone a fundraiser under the new law. (Dellinger is now a Democratic candidate for lieutenant governor.)

Kelley focused on the phrase "personally acquired" in the law. He said that meant the only disclosure required was of "funds the appointee personally accepted from a donor and physically transferred to the campaign, executive committee or political committee."

To make sure he had understood the intent of Perdue and other sponsors, Kelley said, he talked to the legislative staff who drafted the law. He said they support his view "that a narrow construction of the disclosure provision was intended."

Perdue declined to be interviewed for this report. Her spokesman, David Kochman, released a statement saying the legislation was a "starting point" for reform and stronger than the version passed by the House. Easley also declined to be interviewed.

With the opinion in hand, Easley's staff advised his appointees to the board in a memo that they did not have to disclose fundraising if it did not involve collecting the checks.

Shortly afterward, appointees Louis W. Sewell Jr. of Jacksonville and D.M. "Mac" Campbell of Elizabethtown wrote "none" on their fundraising disclosure forms. Interviews with other Easley fundraisers, and an internal Easley campaign document obtained by The News & Observer, show that Sewell helped meet a $125,000 fundraising goal in Onslow County, while the campaign counted on Campbell to help raise $50,000 in Bladen County. (An Easley spokesman, Seth Effron, said neither Easley nor Dave Horne, the campaign treasurer in 2000, could confirm the document's authenticity. Effron said Easley declined to comment on the information within it.)

Another Onslow County fundraiser for Easley, Joe Henderson, said that he, Sewell and another man solicited contributors by phone and held a reception for Easley at an inn that has since been torn down.

Sewell, who also served on the board under former Gov. Jim Hunt, did not return messages left at his home or at work. He is a retired executive with the Golden Corral steakhouse chain. In 2005, Easley awarded him one of the state's highest honors, the Order of the Long Leaf Pine.

Campbell confirmed that he raised money for Easley in 2000 and 2004 by holding fundraisers at his lakefront cottage, but he did not have to disclose his efforts because he did not collect the checks. He cited the Easley memo.

Another appointee, Lanny T. Wilson of Wilmington, said in his 2000 disclosure form that he would follow up with information about his fundraising, but no such documentation is on file with the legislature or the Governor's Office. Wilson said he doesn't remember whether he provided it and said he didn't have to anyway because he did not "personally acquire" contributions.

In the disclosure he filed for his reappointment in 2005, Wilson listed totals he raised for 17 candidates, including Easley. He also wrote that he held a fundraiser for Easley. But other than family members, Wilson does not list the names of any contributors. The form asks for the names of contributors; the law says that appointees are required to disclose contributions.

Some report fully

Three other DOT board members members provided more information.

Cameron W. McRae of Kinston, who owns a string of Bojangles' restaurants, provided a spreadsheet that listed not only contributors, but also everyone he solicited. They contributed $126,000 for Easley in 2000.

G.R. Kindley, the former mayor of Rockingham and a builder, and Paul Waff Jr., an Edenton contractor and developer, also provided lists of contributors. They raised $38,000 and $24,000, respectively.

"I wanted everybody to know who was contributing," Kindley said in an interview. "I think it's important to know."

Waff, who left the board in 2002, said he was appointed after he went to R.V. Owens -- a renowned fundraiser for Easley, state Senate leader Marc Basnight and other Democrats -- to express an interest in a seat.

Easley's appointee for transportation secretary, Lyndo Tippett, a CPA from Fayetteville, was also required to fill out the disclosure form. Like Sewell and Campbell, Tippett wrote "none" where the form asked for the names of those he had collected campaign contributions from. He attached an explanation that said he delivered bundles of contribution checks to the campaign in Raleigh, but he did not collect them from individual contributors. He said in an interview that he did not look to see who wrote the checks or the amounts.

Tippett said his disclosure was a "textbook" example of complying with the law.

Tippett was a member of the Cumberland County steering committee for the campaign, which held two fundraising events. In an interview, Tippett said that he helped organize at least one fundraiser, which Easley attended. He said he had a file on the fundraiser, but he couldn't remember what it contained. He said he didn't know if the file was still available.

"I don't know if it's still there," he said. "The shredder came through town a few months ago and shredded all the files whether it was personal or business. I have no idea at the moment."

The transportation secretary also said it was not his concern what board members reported regarding their fundraising.

"They don't report that to me, so I don't have a problem with that," Tippett said. "Not my issue."

Easley named Sewell and McRae to two of the five newly created at-large seats on the board. Though the three other at-large members were required to have "expertise" in environmental issues, mass transit or government-related finance and accounting, the two seats Sewell and McRae took did not have to meet that requirement. Sewell had to have only "broad knowledge of and experience in transportation issues affecting rural areas." McRae had to be "familiar with the State ports and aviation issues."

The reform law requires Sewell, McRae and the other at-large members to represent the interests of the entire state. But records of an economic development discretionary fund that lawmakers created in 2005 shows that Sewell, McRae and another at-large member, Larry Helms of Union County, have so far directed their allotments -- a total of $5.5 million -- to their home transportation districts. Original article ...

October 31, 2007

Botched paving costly to DOT and NC taxpayers - $21 million

The botched paving job on Interstate in North Carolina cost taxpayers at least $21,000,000 dollars and many months of commuting hardships and misery for drivers.

At the tail end of a multi-year project to implement a major expansion of I-40 between Durham and Chapel Hill, NC, inspectors discovered that miles of new concrete pavement was breaking apart. More studies showed that the top layer of concrete had not been installed correctly and was breaking down even before the project was complete.

The project was already late and had cost taxpayers much more than originally planned and a major part of the work had to be torn up and reworked by contractors. The $21,000,000 repair is yet another demonstration of major mis-management and poor planning within North Carolina's Department of Transportation. The extension added another year of misery for weary commuters traveling the road each day.

Unfortunately for taxpayers, Governor Easley's hand picked director for the DOT, Lindo Tippett, has never admitted any responsibility for the blunder and has remained unscathed while lower level state employees were reprimanded and, in some cases, fired for the mistake. The Governor has not seen fit to replace Mr. Tippett and new reports emerge weekly of additional long postponement or cancellation of many needed major projects and continued severe budget shortfalls as taxpayers foot the bill for gross mismanagement and incompetence in the state's operations.

A new article has appeared in the October issue Asphalt Magazine by the manufacturer of heavy equipment that was used to tear up the broken new concrete and gives an interesting view of the magnitude of work required, done only at night, to undo the botched paving work. The contractor has now completed repairs made under a $21 million project. Interestingly enough the state threatened the contractor with significant fines of $10,000 per hour if workers had not moved out of the way of commuters by morning as the project was carried out.

Read more of this fascinating use of technology to repair one of North Carolina DOT's largest blunders to date....

Asphalt Contractor magazine
October 30th, 2007

Failed concrete overlay milled, replaced with HMA

A failing concrete overlay on I-40 near Raleigh-Durham, NC, was determined by the North Carolina DOT to be in need of replacement. The specifications for the project provided that the concrete overlay be removed by cold-milling and replaced with hot mix asphalt (HMA) each night.

The Lane Construction Corporation was awarded the $21-million project for the North Carolina DOT, and has undertaken the milling, while its Rea Contracting LLC affiliate performed the HMA placement on strict nightly schedules.

"We're grinding anywhere from 3 to 3.5 inches of concrete overlay off the Interstate using a Wirtgen W 2200 cold mill with full lane, 12-foot 6-inch drum," says J. Todd Moore, superintendent of the I-40 project for Lane. "We have approximately 21 lineal miles to do, two lanes eastbound, and two lanes westbound, as well as all off ramps and acceleration lanes."

The existing pavement is three lanes wide each way, with the third (inside) lane made of full-depth concrete, recently reconstructed. The concrete overlay being removed had been placed over existing Portland cement concrete and was experiencing spalling at the joints, and patched "blow-out" potholes where heavy traffic was pulling material from the pavement.

"We have about 290,000 square yards of concrete removal required for this project," says Richard Snow, P.E., construction manager for Lane. "Our average pace of 2,200 lineal feet per night of lane works out to about 2,700 square yards. On weekends we do a lot more with our marathon closures. While we still keep one lane open, we are able to keep the two lanes closed 56 hours straight."

"We're finding both conventional and high early-strength concrete in the overlay, but the W 2200 is chewing right through it all," Moore says. "We've used the W 2200 for scarifying concrete as well, but this 3.5-inch-deep cut is more of a test for the machine during the four hours we work each night."

New open-space tooth pattern

A new open-spaced tooth pattern drum design which applies more horsepower per tooth, but with fewer teeth, was being used on this cold mill.

"We're using Wirtgen teeth with 1.25-inch spacing of teeth on the drum, with some 130 teeth on the drum," Moore says. "We're not using up as many teeth on the drum as before, but it's grinding up the concrete more efficiently, and pulling the material off the existing concrete. It's coming up in a little bit larger chunks, and the milling is more efficient. It's leaving a nice pattern on the pavement, and both the state and the paving contractor are well-pleased."

Nonetheless, Moore and his crews have experimented with the right configuration for the drum and machine.

"At one time we slowed the cutter drum down, but had no success with increasing footage, because teeth were breaking off as the drum was going slower, and not keeping up," he says. "We brought it back to its original speed - about 21 feet per minute, and now things are rolling. Because we're limited at night to what can be repaved before rush hour, I'll open up anywhere from 2,000 to 2,600 feet, depending on how tight the concrete is in our four-hour period."

Thus a given night would see Lane begin milling after 8 p.m. and conclude about midnight, with Rea Contracting paving the next four to five hours, with the last hour striping and removal of the traffic control pattern. "We have to be off the Interstate by 6 a.m., with penalties of $10,000 per hour," Moore says.

Superpave replaces concrete

The concrete overlay was being replaced by two lifts of a Superpave mix, PG 76-24 polymer modified binder, with 9.5 D mm aggregate. The first was a 2-inch lift, followed by a 1.5-inch lift on top to bring to grade. The HMA was provided by Rea Contracting out of its Northern Raleigh plant. North Carolina DOT specified a material transfer vehicle be used between truck and paver.

At midnight, the milling and paving supervisors meet to run numbers as to how far the milling can go that night, so both crews can finish their jobs that morning.

"We see how far we will mill, so we can finish milling and Rea can finish paving, all at a happy medium," Moore says. "We also have to figure in cutter tooth changes, and that will slow us down a little. Right now we do a complete cutter tooth change every 1,000 to 1,100 feet; the more efficiently we can change the 130 milling teeth, and install new ones, the faster we can get back to work."

Lane's complete tooth change using Wirtgen quick-change toolholders will take about 15 minutes.

Hydro-sweeping and infrared drying

Following the W 2200, a standard street sweeper was cleaning the milled surface, followed by a contract hydrovacuum truck which was water-blasting any remaining material off the surface, and vacuuming it into a tank for disposal.

"We're picking up the heavy stuff with the sweeper, and then we have a 36,000 psi-capable hydrovac truck clean the pavement with sprayed water, and vacuum up the water and any fines," Moore says. "This surface has to be totally spotless before we apply our tack coat."

And because the surface has to be bone-dry before the tack coat - and not much time in which to dry - Lane was using an infrared heater truck with generator to dry the milled surface prior to tack and overlay. "The truck has two 195-mph blower fans which blow off any standing water, and heating coils which evaporate any remaining moisture."

Lane's W 2200 with full-lane width drum was giving Lane the power and reliability it needed to keep this project on schedule and in budget.

Moore was finding that the new Eco-Cutter drum from Wirtgen was keeping the job moving along with accrued savings from use of fewer teeth. "This is the first application for which we've used this full-lane drum," Moore says. "This application is nice for the full-lane drum because it's one lane, one way, without having to back up and go. And the drum has a coarser pattern to it. My feeling is, 'the coarser, the better', because the asphalt can hold tighter in the voids than it can in a smoother surface."

Fewer cutting tools on the new Eco-Drum means less resistance to cutting and a higher rate of advance, with lower tool costs per milled cubic yard. These drums, with smaller number of point attack tools, make sure work proceeds more quickly and cost-efficiently.

Despite the fact that the standard-width Eco-Cutter may equipped with only 114 cutting tools, its performance with 1-inch tool spacing is roughly 20 percent higher than that of a standard milling drum with 0.6-inch tool spacing when working in hard asphalt and at a milling depth of 8 inches.

About the Wirtgen W 2200

The W 2200 is designed for big, continuous cold milling projects in which a pavement must be removed mile after mile. The high-horsepower, deep-cutting, high-production

W 2200 lets users mill large projects in a short period of time.

The W 2200 has a standard cutting width of 87 inches, four large D-6 crawler tracks, a milling drum with a high-efficiency mechanical belt drive, and an efficient front-loading system. It has a mechanically driven milling drum and two-part slewing front-end discharge conveyor of variable height. The machine travels on crawler tracks. Robust welded construction with mounts for the individual function modules and superstructures. The tanks for diesel fuel and water are integrated into the chassis. The hydraulic fluid tank forms a separate unit.

Its maximum cutting depth is 14 inches and with the optional Flexible Cutter System, can cut up to 14 feet 1 inch wide. The W 2200 has an operating weight of 96,342 pounds with a 900-hp power plant.

The walk-through operator's platform with access ladder on each side is located in the middle part of the machine. It is equipped with two identical control consoles which can be pivoted and vertically adjusted. Both control consoles and the right-hand driver's seat can be displaced outwards beyond the edge of the machine. The steering and feed control operate with electrical proportional action and are controlled via joysticks.


The Wirtgen information and diagnosis system - called the WIDIS 32 - provides the driver with comprehensive up-to-the-minute information on the current status of the engine and hydraulic system and generates visual and acoustic alarms when necessary. The crawler tracks are suspended from the chassis via round cylinders, the height of which can be adjusted hydraulically. The height of each crawler track can be adjusted individually. The height required for the milling depth is adjusted via the two cylinders at the front, while the rear crawler tracks form a full floating axle. The large lift ensures considerable ground clearance simplifying such difficult maneuvers as reversing or loading and unloading the machine from a low-bed truck.

October 5, 2007

Time for major NC DOT change

Yet another blunder by the NC DOT - this time hiding what tax dollars paid for...

A string of news articles in recent months has underscored poor management, incompetence and arrogance in the NC DOT organization. The $20,000,000 costly blunder on improper pavement on I-40 near Durham and Chapel Hill wasted enough tax dollars to more than cover the gap in funding to allow construction of the urgently needed western segment of I-540 to begin. Inadequate planning and funding of new construction vital to expansion of the state's road systems is often discussed in news articles and the DOT organization still has no plan on how to meet badly needed construction and maintenance projects around the state. And now the Governor has had to step in and order Lindo Tippett, Easley's own appointed DOT Director, to release documents related to a $3.6 million contract with a management consultant firm hired by the DOT to evaluate the DOT's own performance.

It is clear that those in charge of the DOT don't have a clue how to manage the organization, much less handle planning and budgeting to meet transportation infrastructure needs of the state. This is one more in a string of problems popping to the surface with a number of appointments made by Governor Easley to run key parts of the state government.

A News & Observer editorial just out states "All this is an embarrassing miscue. The longer DOT lets it continue, the more the department's reputation and credibility will crack like the concrete on the stretch of I-40 that crumbled under the weight of a previous foul-up."

Read what the editorial reveals about the latest of many blunders within the DOT structure and waste of tax dollars...
News & Observer
October 2, 2007
Editorial

DOT's blackout
State transportation officials go against their responsibility to taxpayers in trying to keep a consultant's report secret

It's as sad as it is outrageous when state officials release documents with sections blacked out to keep secrets from the people those officials are supposed to serve. It shows arrogance -- the agency involved doesn't recognize its obligation to public disclosure -- and it evidences a distrust of the people themselves.

An egregious example of all this has just surfaced at the state Department of Transportation, which has behaved secretively at best in regard to a $3.6 million contract with a management consultant. The outside firm was hired earlier this year to assess the DOT, an agency long troubled by interference, inefficiency and internal discontent.

Contract details were blacked out wholesale in documents released to The News & Observer. Even worse is that DOT officials haven't required the consultants, McKinsey & Co., actually to supply a written report. The consultant's findings are being delivered orally, and behind closed doors.

Simply put, the state is spending $3.6 million for information and advice, but it has nothing to show the public.

Said Mark L. Foster, the DOT's chief financial officer, "No, there is no report .... Read more...

September 29, 2007

Report of NC DOT incompetence hidden from public

An alarming new report provides more evidence that NC's DOT organization is poorly suited to meet transportation needs of the state and reveals the organization is withholding a major consultant review of the DOT paid for by taxpayer dollars. The DOT continues to reflect the incompetence of director Lindo Tippett, appointed by Governor Easley, and the inability of DOT staff in managing thousands of state employees responsible for maintaining NC's road infrastructure and planning what is needed to handle the unprecedented growth in state traffic.

It is clear that the time has come to demand that the DOT director step down and a replacement be appointed that has the knowledge and ability to manage the organization and facilitate planning and funding of what is needed to build and maintain an adequate transportation infrastructure that will allow the state to be competitive.

Results from a comprehensive survey of some 13,000 thousand DOT workers and interviews with at least two dozen key legislators, state officials, business executives and local transportation officials, along with information from follow up discussions, strongly suggests a lack of understanding within the organization about the mission of the DOT and tells of poor use of funds and inadequate project plans and schedules. Mark L. Foster, the department's chief financial officer, confirmed that "DOT employees complained that they lack a shared understanding of their mission." He briefly described other criticisms: "Road projects cost too much time and money. It's hard to figure out who is responsible for any DOT project."

Read the report and learn more about the lack of a "unified vision", deception and confusion in the state's DOT organization...
News and Observer
September 29, 2007
Bruce Siceloff, Staff Writer

Consultants review of DOT under wraps
McKinsey & Co. was asked to prepare a sweeping evaluation of the transportation agency, but DOT and the company are keeping a tight rein on the information

State Department of Transportation officials are paying a consultant $2.5 million to help make the agency more responsive, accountable and transparent.

They are keeping much of the work secret.

Attorneys for DOT and McKinsey & Co., an international management consultant hired in April to evaluate DOT, blacked out several pages of contract details and stamped other pages "CONFIDENTIAL" before DOT released them to The News & Observer.

Other contract documents indicate that McKinsey initially was asked for a candid, sweeping assessment of DOT's "strategic direction and organizational structure." It was expected to file reports in May and June.

DOT has declined to release a word of its consultant's findings. The April 11 contract includes an unusual pledge that DOT will seek McKinsey's permission before making public references to McKinsey or releasing any "reports, analyses or other such materials" it receives from McKinsey.

DOT officials now say they did not request or receive any written reports from McKinsey, whose contract ends in mid-October. Read more...

September 21, 2007

Internet access improving in NC

Access to the internet has become a vital resource for education and helping the state population connect to information needed for everyday living. This is a vital component to help NC citizens increase knowledge required to compete in the 21st century and is emerging as an infrastructure component that is as vital to economic health and prosperity as much as roads, water, sewer and electricity and telecommunications connectivity.

"Increasing statewide access to broadband Internet service enhances economic progress by allowing citizens to have greater access to health care information, education and job-training opportunities and support for small businesses and entrepreneurs," reports Oppie Jordan, economic developer for the Carolinas Gateway Partnership and chairwoman of the e-NC Authority governing commission.

Internet connectivity has increased only 2 percent from the previous study. A new e-NC report shows the percent of area households having the ability to access broadband Internet this year versus last year: Edgecombe, 77.4 percent, up from 75.05 percent; Nash, 76.32 percent, up from 74.17 percent; Wilson, 90.8 percent, up from 87.51 percent; and Halifax, 80.64 percent, up from 77.18 percent.

Read the entire report...
Rocky Mount Telegram
September 20, 2007
Tom Murphy

High-speed Net access inches up

A state report released by the e-NC Authority shows that availability of broadband Internet access in North Carolina is increasing at a nominal rate.

"High-Speed Internet Access in North Carolina: A 100 County Report" reveals that 83.54 percent of North Carolina households have access to broadband Internet services. This is an increase of less than 2 percent from the previous year, said Oppie Jordan, economic developer for the Carolinas Gateway Partnership and chairwoman of the e-NC Authority governing commission. The e-NC Authority's headquarters are located in Raleigh.

"Counties that lack high-speed connectivity are often at a crucial disadvantage in terms of opportunity and prosperity," Jordan said. "I have a hard time believing that the citizens of our state would accept only 83.54 percent of homes having access to broadband Internet services."

Jordan said North Carolina is in the midst of a transformation toward a 21st century, knowledge-based economy.

"Increasing statewide access to broadband Internet enhances economic progress by allowing citizens to have greater access to health care information, education and job-training opportunities and support for small businesses and entrepreneurs," she said.

The e-NC report shows the percent of area households that have the ability to access a broadband Internet connection this year versus last year: Edgecombe, 77.4 percent, up from 75.05 percent; Nash, 76.32 percent, up from 74.17 percent; Wilson, 90.8 percent, up from 87.51 percent; and Halifax, 80.64 percent, up from 77.18 percent.

Major deployment of broadband Internet access in urban communities is nearly done, Jane Patterson, executive director of e-NC Authority, said in the report.

"What we are now trying to do is push for broadband expansion into the most under served areas, which are often rural and economically disadvantaged," Patterson said. "Dial-up won't cut it anymore – plain and simple.

"If broadband connectivity levels in this many homes, schools and businesses is so inadequate, we can't expect companies to thrive and remain competitive, or that our rural children will have a chance to learn the latest technologies and Web-based applications."

Now emerging as infrastructure that is as vital to economic health and prosperity as roads, water, sewer and electricity, advanced telecommunications connectivity, rarely extends into communities that are sparsely populated, Jordan said.

The e-NC Authority is distributing $1.21 million as matching incentive grants for expansion of high-speed Internet service into communities with the lowest levels of connectivity – Jones, Warren, Gates and Greene counties, she said. Original article...

August 21, 2007

I-40 repair completion ends DOT 21.7M blunder


Repair of NC DOT's $21.7 million blunder has ended. The contractor has finished removal and replacement of faulty concrete that was supposed to last for 30 years. A final surface layer will be applied that is intended to make the new surface last for 10 years.


The bottom line - NC DOT failed to make sure proper instructions were given to the original contractor rebuilding a section of I-40 in durham county. Now $21.7 million that could have been used to build new roads or repair damaged ones is gone forever to fix a mistake by the DOT.

This is enough money to eliminate the funding gap that would have allowed construction to begin on the western part of I-540 that is now on indefinite hold. Commuters in the southern and western parts of the area must continue enduring daily backups and extended commutes on crowded roads and town streets with no relief in sight.

Unfortunately the same management of the state's DOT organization is still intact and continuing with the same management style that led to the I-40 funding waste. Accountability is not a word known within the NC DOT and poor management of funds and inability to find ways to secure new funding for needed roads and repairs will be part of life in NC until the current Governor's administration comes to an end.
News & Observer
August 21, 2007
Bruce Siceloff, Staff Writer

Big part of I-40 repairs complete

Lane Construction Corp. ripped out the last of the bad concrete on Interstate 40 in Durham County Monday night -- and finished removing the N.C. Department of Transportation's 10.4-mile mistake.

The on and off ramps on westbound I-40 at N.C. 54 (Exit 273, Chapel Hill) were closed overnight while Lane replaced faulty concrete with fresh asphalt.

That, DOT engineer Eben Miller said Monday evening, completes a major phase of Lane's $21.7-million contract to repair concrete that failed because of DOT's blunder in a widening project in 2003.

The DOT gave the wrong instructions to a different contractor, who incorrectly applied a 3-inch concrete layer to a stretch of I-40. The problem affected two lanes in each direction from N.C. 147 Durham Freeway in Research Triangle Park to U.S. 15-501 and the Orange County line.

The new concrete was supposed to bond with the original concrete beneath it. It was supposed to be good for 30 years.

Instead, the top layer began to expand, buckle, crack and crumble.

So DOT hired Lane to remove the bad concrete and replace it with asphalt. The third inner lane was not affected, and it is still solid concrete.

Later this week, Lane will do some cleanup work.

Next week, probably Monday, Miller said, Lane starts putting down a 5/8-inch layer of special asphalt that will cap all three lanes in each direction (including the inside, all-concrete lane). The material is designed to make the ride smoother and safer and to make the new asphalt last about 10 years. Original article...

August 2, 2007

North Carolina bridges worst in the southeast

According to an August 2, 2007, AAA of the Carolinas statement "North Carolina's highway bridges are in the worst shape of any state in the Southeast, and two Charlotte-area counties -- Burke and Cabarrus -- are at the bottom of the list."

This follows on the heels of the terrible bridge collapse in Minnesota involving a 40 year old "unique design" bridge between Minneapolis and St. Paul.

The report does not say any bridges are in emminent danger of collapse but many are in need of significant repair now. As many as 30 percent of the state's bridges have problems that should be resolved in the near time frame.
The Charlotte Observer
August 2, 2007
Steve Lyttle, The Charlotte Observer

AAA: N.C. bridges need work

AAA of the Carolinas says North Carolina's highway bridges are in the worst shape of any state in the Southeast, and two Charlotte-area counties -- Burke and Cabarrus -- are at the bottom of the list.

Bridge safety figures to become a higher priority item across the country, in the wake of the collapse of a freeway bridge Wednesday evening in Minneapolis. At last report, at least four people were killed in the disaster, and another 20 are missing.

According to the Minneapolis Star-Tribune, the bridge that collapsed was declared "structurally deficient" in 2005.

None of the Carolinas bridges listed by the AAA are in danger of collapsing, the agency said in its February 2007 report. But the AAA said a large percentage of the states' bridges are in need of repair.

In the Carolinas, more than a quarter of bridges were rated as "substandard" by the AAA in its survey this year. That figure was 30.6 percent in North Carolina and lower in South Carolina. Read more...