Showing posts with label Incompetence. Show all posts
Showing posts with label Incompetence. Show all posts

February 7, 2008

Fire LyndoTippett - It's time for him to go

North Carolina's DOT has found itself behind the bulls eye once again after a new state auditor's report reveals that the department has incurred additional costs on behalf of NC taxpayers to the tune of an extra $152 million over the last three years on 390 completed projects. The extra costs are related to mismanagement, poor planning and because of schedule changes, environmental reviews and design changes. The report states that 73 percent of those projects missed their projected construction starts. Forty percent of the projects missed that mark by more than a full year.

According to Les Merritt, NC's State Auditor, "DOT is a multi-billion dollar state agency that appears to operate on hunches and intuition rather than hard data analysis. As a result, taxpayers paid $152.4 million in unnecessary construction costs."

Merritt's report indicated that the auditors found that DOT does not track or analyze delays or successes in its road-building projects, despite repeated warnings and recommendations during the past 10 years from auditors and consultants. The auditors also said that if the department had an effective system for tracking performance, officials might have seen that delays cost taxpayers over $150 million.

"The lack of performance management practices has been pointed out to DOT before," the auditors wrote.

As expected, DOT officials are disputing the findings rather than admitting they happened and are not focusing on working toward solutions. Debbie Barbour, director of preconstruction for the department, claims engineers have only a rough guess of how long a project will take when funding is approved and says the detailed engineering has not been done up front (as it should be). She states that since the engineering work has been done at approval time, the estimated completion date can't take into account problems along the way. She also argues that environmental problems, obtaining permits and other issues are out of control of the department and says it is unfair to say projects are late because of those and other issues.

Signs continue to surface that the DOT is a poorly managed organization and unacceptable practices from the top down cause virtually everything DOT touches to be poorly done, to introduce avoidable significant problems and delays into projects and to cause taxpayers to pay more for substandard work that does not meet growing needs of the state.

It's time for Governor Easley, who takes much of his direction from his staff of buddies that help him make unwise choices and appointments of "good old boys" to state leadership positions, to realize the severity of problems in DOT and other state organizations and fire top leaders like Lyndo Tippett and mid-level management people like Debbie Barbour and at least make a feeble effort to re-establish a little control and get something for the billions of dollars spent on roads and projects while he is still in office.

Read the full article about findings in the study...

News and Observer
February 7, 2008
Dan Kane and Benjamine Niolet, Staff Writers
Delayed road projects cost millions

An audit of three years of completed state Transportation Department projects found many of them finished behind schedule, leading to what auditors say is an additional $150 million in inflation-related construction costs.

"DOT is a multi-billion dollar state agency that appears to operate on hunches and intuition rather than hard data analysis," State Auditor Les Merritt said. "As a result, taxpayers paid $152.4 million in unnecessary construction costs."

The 43-page audit released today looked at 390 highway projects completed between April 2004 and March 2007. Auditors said that 73 percent of those projects missed their projected construction starts. Forty percent of the projects missed that mark by more than a full year, Merritt said.

The audit said that the permitting process, environmental reviews and design changes caused many of the delays.

Department officials say the auditors held the department to an unfair standard. The $150 million figure is oversimplified and doesn't account for some $80 million the department saved by expediting projects within the same time frame.

The auditors based a project's start date and projected completion date on when the transportation board approved money for preliminary engineering. The problem with that method, said Debbie Barbour, director of preconstruction for the department, is that engineers have at that time only a rough guess over how long a project will take. Since no engineering work has been done, the estimated completion date can't take into account problems along the way.

"In developing a project, there are certain things that are outside the department's control, such as obtaining an environmental permit," Barbour said. "We don't really have control of the time frame on every activity in the approval process."

The auditors found that the department does not track or analyze delays or successes in its road-building projects, despite repeated warnings and recommendations during the past 10 years from auditors and consultants. The auditors said that if the department had an effective system for tracking performance, officials might have seen that delays cost taxpayers $150 million.

"The lack of performance management practices has been pointed out to DOT before," the auditors wrote.

But department officials say the department has implemented several new programs and processes since 2001 that wouldn't have been evident in the time period the auditors examined. The department has worked with the state Department of Environment and Natural Resources to streamline environmental permitting. The department measures whether it met target dates for acquiring property for a project or opening bids.

And the department has spent $3.6 million to hire a consultant to help officials change the way the department does business.

Bill Rosser, the state highway administrator said that the department works hard to finish projects on time, but road building is a complex and expensive business. Rosser said if the auditors looked at a newer set of projects, the findings would be much different.

"We would like to be responsive and deliver our projects," Rosser said. "We're always looking at the way the process works." Original source ...

October 31, 2007

Botched paving costly to DOT and NC taxpayers - $21 million

The botched paving job on Interstate in North Carolina cost taxpayers at least $21,000,000 dollars and many months of commuting hardships and misery for drivers.

At the tail end of a multi-year project to implement a major expansion of I-40 between Durham and Chapel Hill, NC, inspectors discovered that miles of new concrete pavement was breaking apart. More studies showed that the top layer of concrete had not been installed correctly and was breaking down even before the project was complete.

The project was already late and had cost taxpayers much more than originally planned and a major part of the work had to be torn up and reworked by contractors. The $21,000,000 repair is yet another demonstration of major mis-management and poor planning within North Carolina's Department of Transportation. The extension added another year of misery for weary commuters traveling the road each day.

Unfortunately for taxpayers, Governor Easley's hand picked director for the DOT, Lindo Tippett, has never admitted any responsibility for the blunder and has remained unscathed while lower level state employees were reprimanded and, in some cases, fired for the mistake. The Governor has not seen fit to replace Mr. Tippett and new reports emerge weekly of additional long postponement or cancellation of many needed major projects and continued severe budget shortfalls as taxpayers foot the bill for gross mismanagement and incompetence in the state's operations.

A new article has appeared in the October issue Asphalt Magazine by the manufacturer of heavy equipment that was used to tear up the broken new concrete and gives an interesting view of the magnitude of work required, done only at night, to undo the botched paving work. The contractor has now completed repairs made under a $21 million project. Interestingly enough the state threatened the contractor with significant fines of $10,000 per hour if workers had not moved out of the way of commuters by morning as the project was carried out.

Read more of this fascinating use of technology to repair one of North Carolina DOT's largest blunders to date....

Asphalt Contractor magazine
October 30th, 2007

Failed concrete overlay milled, replaced with HMA

A failing concrete overlay on I-40 near Raleigh-Durham, NC, was determined by the North Carolina DOT to be in need of replacement. The specifications for the project provided that the concrete overlay be removed by cold-milling and replaced with hot mix asphalt (HMA) each night.

The Lane Construction Corporation was awarded the $21-million project for the North Carolina DOT, and has undertaken the milling, while its Rea Contracting LLC affiliate performed the HMA placement on strict nightly schedules.

"We're grinding anywhere from 3 to 3.5 inches of concrete overlay off the Interstate using a Wirtgen W 2200 cold mill with full lane, 12-foot 6-inch drum," says J. Todd Moore, superintendent of the I-40 project for Lane. "We have approximately 21 lineal miles to do, two lanes eastbound, and two lanes westbound, as well as all off ramps and acceleration lanes."

The existing pavement is three lanes wide each way, with the third (inside) lane made of full-depth concrete, recently reconstructed. The concrete overlay being removed had been placed over existing Portland cement concrete and was experiencing spalling at the joints, and patched "blow-out" potholes where heavy traffic was pulling material from the pavement.

"We have about 290,000 square yards of concrete removal required for this project," says Richard Snow, P.E., construction manager for Lane. "Our average pace of 2,200 lineal feet per night of lane works out to about 2,700 square yards. On weekends we do a lot more with our marathon closures. While we still keep one lane open, we are able to keep the two lanes closed 56 hours straight."

"We're finding both conventional and high early-strength concrete in the overlay, but the W 2200 is chewing right through it all," Moore says. "We've used the W 2200 for scarifying concrete as well, but this 3.5-inch-deep cut is more of a test for the machine during the four hours we work each night."

New open-space tooth pattern

A new open-spaced tooth pattern drum design which applies more horsepower per tooth, but with fewer teeth, was being used on this cold mill.

"We're using Wirtgen teeth with 1.25-inch spacing of teeth on the drum, with some 130 teeth on the drum," Moore says. "We're not using up as many teeth on the drum as before, but it's grinding up the concrete more efficiently, and pulling the material off the existing concrete. It's coming up in a little bit larger chunks, and the milling is more efficient. It's leaving a nice pattern on the pavement, and both the state and the paving contractor are well-pleased."

Nonetheless, Moore and his crews have experimented with the right configuration for the drum and machine.

"At one time we slowed the cutter drum down, but had no success with increasing footage, because teeth were breaking off as the drum was going slower, and not keeping up," he says. "We brought it back to its original speed - about 21 feet per minute, and now things are rolling. Because we're limited at night to what can be repaved before rush hour, I'll open up anywhere from 2,000 to 2,600 feet, depending on how tight the concrete is in our four-hour period."

Thus a given night would see Lane begin milling after 8 p.m. and conclude about midnight, with Rea Contracting paving the next four to five hours, with the last hour striping and removal of the traffic control pattern. "We have to be off the Interstate by 6 a.m., with penalties of $10,000 per hour," Moore says.

Superpave replaces concrete

The concrete overlay was being replaced by two lifts of a Superpave mix, PG 76-24 polymer modified binder, with 9.5 D mm aggregate. The first was a 2-inch lift, followed by a 1.5-inch lift on top to bring to grade. The HMA was provided by Rea Contracting out of its Northern Raleigh plant. North Carolina DOT specified a material transfer vehicle be used between truck and paver.

At midnight, the milling and paving supervisors meet to run numbers as to how far the milling can go that night, so both crews can finish their jobs that morning.

"We see how far we will mill, so we can finish milling and Rea can finish paving, all at a happy medium," Moore says. "We also have to figure in cutter tooth changes, and that will slow us down a little. Right now we do a complete cutter tooth change every 1,000 to 1,100 feet; the more efficiently we can change the 130 milling teeth, and install new ones, the faster we can get back to work."

Lane's complete tooth change using Wirtgen quick-change toolholders will take about 15 minutes.

Hydro-sweeping and infrared drying

Following the W 2200, a standard street sweeper was cleaning the milled surface, followed by a contract hydrovacuum truck which was water-blasting any remaining material off the surface, and vacuuming it into a tank for disposal.

"We're picking up the heavy stuff with the sweeper, and then we have a 36,000 psi-capable hydrovac truck clean the pavement with sprayed water, and vacuum up the water and any fines," Moore says. "This surface has to be totally spotless before we apply our tack coat."

And because the surface has to be bone-dry before the tack coat - and not much time in which to dry - Lane was using an infrared heater truck with generator to dry the milled surface prior to tack and overlay. "The truck has two 195-mph blower fans which blow off any standing water, and heating coils which evaporate any remaining moisture."

Lane's W 2200 with full-lane width drum was giving Lane the power and reliability it needed to keep this project on schedule and in budget.

Moore was finding that the new Eco-Cutter drum from Wirtgen was keeping the job moving along with accrued savings from use of fewer teeth. "This is the first application for which we've used this full-lane drum," Moore says. "This application is nice for the full-lane drum because it's one lane, one way, without having to back up and go. And the drum has a coarser pattern to it. My feeling is, 'the coarser, the better', because the asphalt can hold tighter in the voids than it can in a smoother surface."

Fewer cutting tools on the new Eco-Drum means less resistance to cutting and a higher rate of advance, with lower tool costs per milled cubic yard. These drums, with smaller number of point attack tools, make sure work proceeds more quickly and cost-efficiently.

Despite the fact that the standard-width Eco-Cutter may equipped with only 114 cutting tools, its performance with 1-inch tool spacing is roughly 20 percent higher than that of a standard milling drum with 0.6-inch tool spacing when working in hard asphalt and at a milling depth of 8 inches.

About the Wirtgen W 2200

The W 2200 is designed for big, continuous cold milling projects in which a pavement must be removed mile after mile. The high-horsepower, deep-cutting, high-production

W 2200 lets users mill large projects in a short period of time.

The W 2200 has a standard cutting width of 87 inches, four large D-6 crawler tracks, a milling drum with a high-efficiency mechanical belt drive, and an efficient front-loading system. It has a mechanically driven milling drum and two-part slewing front-end discharge conveyor of variable height. The machine travels on crawler tracks. Robust welded construction with mounts for the individual function modules and superstructures. The tanks for diesel fuel and water are integrated into the chassis. The hydraulic fluid tank forms a separate unit.

Its maximum cutting depth is 14 inches and with the optional Flexible Cutter System, can cut up to 14 feet 1 inch wide. The W 2200 has an operating weight of 96,342 pounds with a 900-hp power plant.

The walk-through operator's platform with access ladder on each side is located in the middle part of the machine. It is equipped with two identical control consoles which can be pivoted and vertically adjusted. Both control consoles and the right-hand driver's seat can be displaced outwards beyond the edge of the machine. The steering and feed control operate with electrical proportional action and are controlled via joysticks.


The Wirtgen information and diagnosis system - called the WIDIS 32 - provides the driver with comprehensive up-to-the-minute information on the current status of the engine and hydraulic system and generates visual and acoustic alarms when necessary. The crawler tracks are suspended from the chassis via round cylinders, the height of which can be adjusted hydraulically. The height of each crawler track can be adjusted individually. The height required for the milling depth is adjusted via the two cylinders at the front, while the rear crawler tracks form a full floating axle. The large lift ensures considerable ground clearance simplifying such difficult maneuvers as reversing or loading and unloading the machine from a low-bed truck.